About the Project
The work in the Highway 50 – Section 2 project took place in the urban area of Jerusalem and included:
- Earthworks covering an area of 65,000 square meters
- Construction of the Nebnishi Bridge over the Begin Road interchange and Benvenisti Street, involving road source excavation over an area of approximately 4,200 square meters
- Construction of the Refaim Bridge over the railway track, including road source excavation over an area of about 10,200 square meters
- Building of supporting walls from retaining walls and cast-in-place concrete on-site covering an area of around 7,000 square meters
- Road pavement with an area exceeding 48,000 square meters
- Infrastructure works, electrical works, communication works, subterranean water infrastructure and drainage, including development works, traffic arrangements, and pavement.
Client: Moriah Jerusalem Development Corporation
Period of Construction: 2012-2015
Financial Scope: NIS 120 million